What needed to be solved

The client required a complete electrical infrastructure system for a new table-water production facility in Abuja. The installation needed to support production equipment, water-treatment systems, packaging machinery, lighting, administrative areas and other auxiliary loads while providing reliable standby power for continuous factory operations.

02 · Solution Delivered

How Humelix responded

Humelix executed the electrical infrastructure from the construction stage through installation and preparation for final commissioning. The scope included heavy-duty conduit installation, cable containment and routing, distribution infrastructure, dedicated production-equipment circuits, lighting and socket circuits, and provision for integration of a 500 kVA Mikano standby generator. Conduits and electrical pathways were coordinated with the structural works before concrete casting to achieve a protected, organised and professional installation.

03 · Result / Outcome

The operational result

Humelix delivered a structured industrial electrical infrastructure capable of supporting the factory's production and auxiliary electrical loads. The installation provided dedicated circuits for critical equipment, organised power distribution and standby power provision through the 500 kVA Mikano generator, establishing a reliable electrical backbone for factory operations.

Equipment / Materials

What supported the work

500 kVA Mikano diesel generator; 4C × 240 mm² XLPE/SWA/PVC copper main feeder cable; 4C × 120 mm² copper distribution feeder; 4C × 70 mm² copper sub-main cable; 4C × 35 mm² copper equipment feeder; 16 mm² and 10 mm² copper cables for dedicated equipment circuits; 6 mm² copper cable for high-load final circuits; 4 mm² copper cable for dedicated power circuits; 2.5 mm² copper cable for socket outlets; 1.5 mm² copper cable for lighting circuits; 20 mm, 25 mm and 32 mm heavy-duty PVC conduits; industrial distribution boards, MCCBs/MCBs, junction boxes, cable accessories, earthing conductors and associated electrical installation materials.

Safety Approach

How the site was controlled

Humelix implemented controlled conduit routing, secure fixing before concrete casting, cable segregation, appropriate circuit protection, equipment earthing and safe distribution practices. Installation activities incorporated PPE, isolation procedures, inspection of concealed services, continuity checks, insulation testing and electrical verification before energisation and commissioning.

Technical reviewSite requirements, service scope and practical constraints are reviewed before recommendations.
Safe deliveryWork is aligned with safety controls, clean execution and client-site protection.
Handover supportCompleted work is closed with guidance, next steps and aftercare awareness.
Extended Outcome

Operational result

The completed infrastructure provides a scalable electrical distribution platform for table-water production, treatment, packaging, lighting and administrative operations. The system was structured to improve maintainability, minimise unnecessary exposed wiring and facilitate future equipment additions and electrical upgrades.

Need a similar result?

Request a similar electrical project consultation.

Share your location, building type and project condition. Humelix will review the right next step.